During the seal coating period,
users will not be directed to an alternate route – rather, please be aware of
the project, use the shoulder when traveling around the work area, and, when
appropriate, walk bikes around the work area.
Work on the Prairie Trail begins
Tuesday, July 31st. It will
start where the Prairie Trail intersects the Centennial Trail north of
Riverstone and the work will continue to Huetter Road. The nearly 4 ½ miles of Prairie Trail should
be completed by August 3rd.
Work on the Centennial Trail
begins Monday, August 6th. It
will start at Higgins Point at the east end of the trail, working west. Through August 10th, work will be
done on the section of trail from Higgins Point to Riverstone Park, which
includes the preparation of all shoulder work on the Class 1 section of the
trail.
Beginning August 13th,
the section of trail from Higgins Point to Riverstone Park will be seal coated.
Also during the week of August
13th, trail patch and repair work between I-90/Northwest Boulevard
and Highway 41 will be completed on the Centennial Trail. During the week of August 20th,
crews will be crack filling and seal coating this same stretch of trail.
Between August 27th
and September 7th, the remainder of Centennial Trail from Highway 41
to the Idaho/Washington state line will be completed, barring any bad weather.
For our trail enthusiasts –
please know that we’ll have spotters in front of and in back of the
construction to remind people to slow down and ride on the shoulders. For more information, please contact the
Parks Department at 769-2252.