The
scope of the project includes the overlay of approximately 37 blocks of city
streets including:
A, B, C, and D Streets from Milwaukee Drive to Virginia
Avenue (Forest Cemetery).
Milwaukee Drive from Government Way to Idaho
Avenue.
Browne Avenue from Government Way to Milwaukee
Drive.
Idaho and Virginia Avenues from Government Way to Lincoln Way.
Lincoln Way from Idaho Avenue to Walnut
Avenue.
The
schedule for the contractor will begin on July 12th with the milling
of asphalt, followed by a 1 ½” overlay of asphalt and then raising all
utilities to grade. The work will be
accomplished during daytime hours.
The
overlay project is scheduled to be completed by the end of July, weather
pending.
If
you have any questions regarding the 2012 Overlay Project, please call Dennis Grant at 769-2398 or email him
at dennisg@cdaid.org.