Wednesday, May 2, 2012

Government Way Road Construction Begins May 7th


With sanitary sewer installation work completed on Government Way from Dalton to Hanley Avenues, construction of the roadway is scheduled to begin on May 7, 2012 with the mobilization of equipment onto the site, and with an anticipated completion date in mid-September 2012.
 

Construction of the new city water main along the west side of Government Way will run concurrently with the construction of a new water main for the Dalton Water District on the east side of the road. The roadway construction along with the installation of a storm sewer main will follow shortly thereafter. The roadway will be open for two way travel, however, construction and delays will be continuous through September of 2012 in that portion of the road corridor.
 

This is an Idaho Transportation Department project, utilizing Federal Highway Administration (FHWA) funds with the City of Coeur d’Alene as the local sponsor. For more information, please contact 769-2228.